I. phase of modenization (recostruction of the existing runway)

18.07.2006
Modernization of Karlovy Vary Airport - I. and II. Stage
The recostruction of the runway was accomplished during the I. stage of Karlovy Vary Airporet modernization. Construction works started 1. November 2005. The aim of the project was the improvement of PCN and the adjustement of the RWY in the longitudinal axis because of the air traffic safety increase... | show the whole text

12.06.06
The 3. Phase of the I. Stage of Karlovy Vary Airport modernization finished
Karlovy Vary Airport was reopened for the air traffic after more than 80 days 28 May 2006 at 2 p.m. Herewith finished the 3. Phase of building works in the frame of the project 'I. stage of the Airport Karlovy Vary modernization - PCN emprovement of the RWY 11-29 at the LKKV'... | show the whole text

18.05.06
To the term of planned restoration of air traffic it only remains 8 days
Current information to work flow | show the whole text

12.04.06
Press news
The negotiations among the Karlovy Vary Region, the airport operator and the constructor of the RWY reconstruction in the frame of the project "Modernization of Karlovy Vary Airport - I. Stage" were finished to the present day. With regard to the actual development of the situation and unplanned closure of the airport was made an agreement about keeping the ... | show the whole text

08.03.06
Airport Karlovy Vary is closed
The company Airport Karlovy Vary Ltd. was forced to close temporary with regard to the air trafic safety The International Airport Karlovy Vary today at 2 p. m. local time. The reason for this decision are continuing construction works in the frame of the project "Modernization of Karlovy Vary Airport - I. Stage." ... | show the whole text

25.02.06
The project "Modernization of Karlovy Vary Apt." - I. Stage enters its 2. phase; the Airport runway has been shortened
Starting on 01.02.2006 building work regarding the project 'Modernization of Karlovy Vary Airport - I. Stage, PCN Improvement of RWY 11-29' entered its 2. phase which followed the completion of the 1. phase preparative construction work ... | show the whole text

II. phase of modernization (reconstruction of the runway supporting facilities)

12.04.06
Press news : Airport Karlovy Vary started the II. stage of modernization
The project "Modernization of Karlovy Vary Airport" follows the I. stage of the modernization and includes the reconstruction of the airport lighting system which is one of the most important activities from the point of wiew of the reinsurance of the yearly airport availability and for the improvement of provided services and air traffic safety... | show the whole text

NUTS2 SEVEROZÁPAD

www.nuts2severozapad.cz

www.europa.eu

Updated: 21.01.2016
Homepage ~ Passengers and Guests ~ Company ~ For crew ~ Media ~ Site Map ~ Links
© 2017 Airport Karlovy Vary Ltd. ~ Powered by: BeInside.cz